EVALUASI EFISIENSI BIAYA DAN WAKTU ANTARA METODE KONVENSIONAL DAN PRACETAK DALAM PEKERJAAN DRAINASE U-DITCH DI RUAS JALAN NASIONAL JAMBI

Authors

  • Bugie Rastapi Iskandar Universitas Sangga Buana
  • Dody Kusmana Universitas Sangga Buana

DOI:

https://doi.org/10.32897/simteks.v4i2.3949

Keywords:

Efficiensy, Cost, Time, Drainage, Conventional

Abstract

Cost and time efficiency are two crucial aspects that influence the success of a construction project. Conventional methods are usually used because they are considered more flexible and easily adapted to field conditions. However, the precast method is increasingly in demand because it is claimed to be more efficient and faster in implementation. This research uses a case study approach by collecting primary and secondary data from planned work. Cost data is obtained from the detailed cost budget (RAB), while time data is taken from the project implementation schedule (time schedule). The analysis was carried out by comparing the total costs and time duration between conventional and precast methods using the 2018 Bina Marga Specifications.

The research results show that the precast method has advantages in time efficiency, with an average construction time that is shorter than conventional methods. However, in terms of costs, precast methods tend to be more expensive in the initial stages due to the high production costs of precast elements.

References

D. R. Siregar, M. Mirnawati, L. A. Hasugian, R. K. L. Tobing, And N. Hidayat, “Evaluasi Dampak Aspek Sosial Dan Aspek Ekonomi Pada Pembangunan Drainase,” Jurnal Sains Dan Teknologi, Vol. 5, No. 2, Pp. 606–612, 2023.

A. Yunianta And B. H. Setiadji, Sistem Drainase Jalan Raya Yang Berkelanjutan. Tohar Media, 2022.

D. Fairizi, “Analisis Dan Evaluasi Saluran Drainase Pada Kawasan Perumnas Talang Kelapa Di Subdas Lambidaro Kota Palembang,” Jurnal Teknik Sipil Dan Lingkungan, Vol. 3, No. 1, Pp. 755–765, 2015.

A. Risdiyanti And S. Siswoyo, “Analisa Perbandingan Biaya Dan Waktu Antara Metode Konvensional Dan Pracetak (Studi Kasus: Underpass Bundaran Satelit Mayjend Sungkono Surabaya),” Axial: Jurnal Rekayasa Dan Manajemen Konstruksi, Vol. 6, No. 2, Pp. 69–78, 2018.

R. E. Falah, “Analisis Biaya Pekerjaan Drainase Berdasarkan Metode Konvensional Dengan Metode Pracetak U Ditch (Analysis Of The Cost Of Carrying Out Drainage Work Based On Conventional Methods With Precast Methods),” 2019.

Published

2024-09-30